top of page

South Shore Boulevard Construction Update

Updated: Aug 8, 2022

The Lake Links trail construction and utility work along South Shore Boulevard is moving along nicely.



"Construction is underway and will last through the fall. The first phase of pavement removal (Bellaire Avenue to East County Line Road) is complete. Additional pavement removal will take place later in the summer.


"Work on the water main will continue through late July. Short-term, temporary water shut offs will be in place. Individual homeowners will be contacted if their property will be impacted.


"South Shore Boulevard is closed to traffic in both directions from White Bear Avenue to County Road F. A signed detour is in place using White Bear Avenue, County Road F and East County Line Road. Residential access will be maintained throughout the project."


For cyclists, the Lake Links Association recommends traveling via Hazel to Lilac to McKnight to County Road F.

Our Lake Links South Shore Boulevard liaison Greg Bartz has provided lots of photos:









305 views0 comments

Recent Posts

See All
Post: Blog2_Post
bottom of page